The Gantt Chart shows project tasks related to time. The Gantt Chart could include:

  • Project tasks in the order they will be started
  • Start date - planned and actual
  • End date  - planned and actual
  • Duration - planned and actual
  • Completion status
  • Any specific events or cut off dates

Dependencies can be shown with arrows that link tasks showing when a task can be started in relation to other tasks. 

  • Finish to Start (FS): The task cannot start before a related task ends
  • Start to Start (SS): The task cannot start until a related task starts
  • Finish to Finish (FF): The task cannot end before a related task ends
  • Start to Finish (SF): The task cannot end before a related task starts

Gantt Chart
Attribution 2.0 Generic (CC BY 2.0) - klarititemplateshop

Text and images Copyright © Spreadsheet Templates

Use of this website is under the conditions of our Terms of Service.

Privacy is important and our policy is detailed in our Privacy Policy.

See the Spreadsheet Templates Cookie Policy for our use of cookies and the user options available.