Gantt Chart Layout

The Gantt Chart shows project tasks related to time. The Gantt Chart could include:

  • Project tasks in the order they will be started
  • Start date - planned and actual
  • End date  - planned and actual
  • Duration - planned and actual
  • Completion status
  • Any specific events or cut off dates

Dependencies can be shown with arrows that link tasks showing when a task can be started in relation to other tasks. 

  • Finish to Start (FS): The task cannot start before a related task ends
  • Start to Start (SS): The task cannot start until a related task starts
  • Finish to Finish (FF): The task cannot end before a related task ends
  • Start to Finish (SF): The task cannot end before a related task starts

Gantt Chart